|
|
|
COMMENTS ON WIDEWATERS
SDEIS
September 15, 2003
Prepared by: Young, Sommer ..., LLC
Attorneys for KNGG
Executive Woods
5 Palisades Drive
Albany, NY 12205
518) 438-9907
Jeffrey S. Baker, Esq.
I. Introduction Kinderhook Neighbors for Good Growth
("KNGG") submit these comments on the Supplemental Draft Environmental Impact
Statement ("SDEIS") for the Widewaters Commons Shopping Center ("Widewaters" or
the "Project"). These comments are in addition to the comments submitted in
November 2002 on the original DEIS. At that time, KNGG noted the glaring
deficiencies in many aspects of the DEIS and the project itself and protested
that the Planning Board could not continue its SEQRA review without correcting
the deficiencies of the DEIS in a Supplemental EIS. Fortunately the Planning
Board recognized its error in accepting the DEIS and ordered the preparation of
a SEIS. However, the scope of the SDEIS was limited and did not address all of
the deficiencies in the DEIS. Moreover, Widewaters was not directed to respond
to the DEIS comments as part of the SDEIS. Therefore, KNGG reasserts its
comments of November 2002 and puts Widewaters and the Planning Board on notice
that any new information contained in a FEIS which was not previously available
for public comment, must be provided in another SEIS to allow for meaningful
comment.
While the foregoing comment concerned missing
elements from the DEIS which were not covered in the SDEIS, there are also
on-going problems with new material submitted since the SDEIS was accepted
and released for public comment. Specifically, upon information and belief
it appears that Widewaters has submitted architectural renderings and
design details for the project which are completely different from what is
included in the SDEIS. Those submittals have not been distributed to
involved agencies or interested parties and thus those parties have not
been given an opportunity to comment on the submissions. Until those
materials are made publicly available and a reasonable time frame is
provided for comment, the Planning Board cannot consider continued
revisions to the design elements of the project.
A
Taken as a whole and evidenced by the
numerous public comments submitted to date, the Widewaters project is out
of scale with the community and is located on a parcel which exacerbates
its problems of scale without providing sufficient community benefits.
Contrary to the tone of much of the public discussion fomented by
Widewaters, this is not an issue of the desirability of a new supermarket
in Kinderhook. KNGG has long supported diversity and competition in
shopping alternatives. The issue is the size of the project and the
unnecessary problems it will cause the community by being located on this
parcel. As the SDEIS demonstrates, the location at a problematic
intersection only compounds the existing problems and the preferred way of
dealing with the situation by a roundabout will fundamentally alter the
character of this section of Kinderhook and change the traffic patterns in
the area. There are significant concerns as to whether such a change is
beneficial and desired by the majority of the people in the town.
Notwithstanding general statements of support from NYSDOT, this is not a
NYSDOT project but rather a proposal from an private developer and NYSDOT
has simply opined that the only possible means of dealing with the traffic
is by a roundabout. It is entirely within the Planning Board’s authority
to determine that this project, with its environmental problems is
inappropriate for this site and not permitted. It is not the
responsibility of the Planning Board to make a project work on a difficult
site - it is the responsibility of the applicant to choose a site that
minimizes or avoids adverse impacts. Where the developer has chosen an
inappropriate site, it is incumbent upon the Planning Board to reject the
project.
Set forth below are KNGG’s comments on the
SDEIS organized by the subject matter. Also attached hereto are additional
comments from Sara Richards and Mark Litteken. Ms. Richards and Mr.
Litteken are on the Board of Directors of KNGG and the attached comments
were also presented at the August 27, 2003 public hearing on the SDEIS.
Also attached are comments on the traffic section provided by KNGG’s
traffic consultant Vollmer Associates. Finally, the comments of Howard
Brandston regarding the impacts from and design of the project lighting
are also included. Mr. Brandston’s comments were also presented at the
public hearing. In addition to these comments, many members of KNGG are
sending comments directly to the Planning Board and should be given full
consideration.
II. Traffic
KNGG’s comments on traffic are supported by
the analysis provided by Vollmer Associates, LLP.
A copy of Vollmer’s comments are attached as
Ex. A.
1. As noted in KNGG’s comments on the DEIS,
Widewaters failed to compile accurate data for existing traffic conditions
by failing to collect data during a period of normally heavy traffic.
Instead, Widewaters collected data in mid-August when school traffic is
non-existent and other traffic is traditionally lighter due to vacation
schedules. In the SDEIS Widewaters claims to have supplemented its traffic
analysis with additional traffic counts, however that data is not supplied
in the SDEIS.
2. In the DEIS, the project only proposed
adding project access to the existing intersection and changing the
signalization. As such it was acceptable for that traffic study to only
consider the impact from the project on the
intersection and thus only look at the afternoon peak travel time to
assess the project’s impact. In the SDEIS, however, the proposal is for a
roundabout that will need to operate under all conditions and not just
those associated with peak operation of the shopping center. As lead
agency, the Planning Board has the responsibility to determine that this
proposed change to the primary intersection in the town works under all
conditions, particularly the morning commute. However, the SDEIS is
absolutely devoid of any information on morning traffic conditions and the
impacts from the roundabout on the morning commute. Widewaters has not
supplemented its traffic study with a morning traffic count and has not
modeled the roundabout for the morning peak. As noted by Vollmer, such an
analysis is a critical flaw as one cannot extrapolate morning conditions
from evening conditions and without raw data and a model run, it is
impossible to predict what the effect will be. Furthermore, the data
supplied by NYSDOT is not a complete traffic study and cannot substitute
for a comprehensive analysis. If this project were to enjoy further
consideration, Widewaters must be directed to conduct a complete traffic
study that includes AM peak travel.
3. Vollmer also points out that Widewaters’
traffic analysis is essentially comparing apples to oranges as it attempts
to argue that use of the roundabout will provide an acceptable LOS.
Vollmer notes that Widewaters has not supplied the necessary reports from
its computer model using the Webster Method which is the only accepted
means of evaluating compliance with the Highway Capacity Manual LOS. The
HCM does not use the percentile delay method for LOS. There can be no
independent verification of Widewaters’ representations without the proper
computer runs presented in the accepted format. Considering Widewaters’
less than stellar record of refusing to provide details and supporting
information to the Planning Board and its misrepresentation of the facts
of its project, it is necessary that the Planning Board’s consultants and
the public have all of the necessary information to verify Widewaters’
claims.
4. Vollmer also notes that Widewaters has not
used NYSDOT’s standard software package for analyzing roundabouts - Rodel.
Widewaters should re-analyze the roundabout using the standard software
package and provide the output data for review.
5. In less than 20 years, by Widewaters own
analysis, the roundabout will be operating beyond capacity and in a
failure condition. Widewaters has refused to provide even preliminary
design details to show that there is an adequate right-of-way for the
current design, let alone future needs. The Planning Board should require
a complete survey demonstrating sufficient right-of-way for now and the
future. Any possible relocation of the roundabout into the Widewaters
project must be taken into account now and changes made to the Widewaters
site plan since such changes will alter the design of the interior
road-way, parking and the aesthetics of the project.
6. Vollmer notes that roundabouts remain a
novel approach without a lot of practical experience in their long-term
viability, especially when they involve five-legged intersections and
NYSDOT also considers them as "experimental". If the project were to be
approved, then the Planning Board should require Widewaters to undertake a
post-construction traffic study to gauge the effectiveness of the
roundabout and provide for any alterations to the roundabout to correct
any design deficiencies. The study should be conducted 2 years after the
project is completed and include new traffic counts, capacity analysis and
a comparison of the actual results to those of the original study and
should include an accident analysis. Widewaters should be required to post
a bond at this time to cover both the cost of the post-construction study
and the potential necessary improvements. There is precedent for such a
requirement on the developer. When Pyramid was proposing the Palisades
Center Mall in Nyack, the Planning Board required Pyramid to post a bond
for a post-construction traffic study and the cost of further
signalization if it was determined that it was required.
7. The SDEIS does not attribute any growth
factors for the driveways into the project when it is calculating future
growth in the area and capacity of the roundabout to handle the growth.
Unlike an office park or similar type of development, use of this shopping
center, especially the supermarket will continue to grow as the area grows
and it is simplistic to claim that the trip generation figures and use of
the driveways will not change in the future. As Vollmer notes, a
sensitivity analysis of the driveways is required.
8. It does not appear that the roundabout has
been designed in accordance with NYSDOT and FHWA guidelines for
roundabouts. While strict compliance with those guidelines is not
required, Widewaters must clearly discuss where it is diverging from those
guidelines, explain the need for the difference and the potential impacts
from the break with the guidelines.
9. The SDEIS is less than clear about
Widewaters’ responsibility for constructing the improvements if they are
approved. Widewaters must specifically commit to paying for all of the
necessary traffic improvements including the roundabout and the new
traffic signal at the intersection of Route 9 and Main Street.
Particularly in regard to the latter, while that intersection is already
operating at an undesirable LOS, by Widewaters’ own analysis, its project
will exacerbate the situation and Widewaters is responsible for the
additional costs. While KNGG does not support approval of the project, any
approval must include a condition that a building permit for the project
will not be issued until Widewaters has obtained all necessary permits for
the traffic improvements and a Certificate of Occupancy should not be
issued until all of the traffic improvements have been completed. These
conditions are necessary to assure that if the project is built, all of
the mitigation measures are properly in place before the impacts of the
project are imposed upon the town.
III. Noise
In its noise impact analyses, Widewaters
again appears to comply with the mandate of the Planning Board and on
initial impression gives the indication of presenting a comprehensive and
accurate assessment of the noise impacts from the project. However, a
careful consideration of Widewaters’ own analyses as
well as an accurate application of DEC’s noise assessment guidelines makes
it apparent that the project will result in significant noise impacts on
surrounding properties. After project completion the noise generated from
Widewaters Commons will be intrusive and objectionable to neighboring
residential uses and will effectively preclude development of currently
vacant property in accordance with its current zoning.
1. The SDEIS understates the noise impacts by
mischaracterizing the thresholds identified in DEC’s Guidance Document
"Assessing and Mitigating Noise Impacts" Revised June 3, 2003. Widewaters
focuses on using the Leq sound measurement which is an
equalized sound pressure reading over time and attempts to average out the
sound levels. By contrast the L90 measurement is generally
accepted as the best measure of background sound since it establishes the
level of sound exceeded 90 % of the time. DEC’s guidance document
recognizes the use of the L90 as a better
measurement tool. (DEC Guidance, p. 12).
2. The SDEIS also provides an incomplete
catalogue of the intrusiveness of noise levels. While the SDEIS properly
quotes the DEC guidance on increases of 3-6 dB, it omits to point out that
increases greater than 6 dB require careful scrutiny and assessment and
"that increases approaching 10 dB result in a perceived doubling of Sound
Pressure Level. . . . An increase of 10 dB(A) deserves consideration of
avoidance and mitigation measures in most cases" (DEC Noise Guidance p.
13-14). Furthermore, the DEC Guidance notes that increases of 5-10 dB are
considered intrusive and increases over 10 dB are very
noticeable.
3. Using Widewaters own analysis but looking
at the measurements which provide the most accurate picture of the change
in the environment, it is clear that the project will have a significant
and unmitigated adverse impact. To measure the change in the background
noise level a comparison must be made to the daytime and nighttime
L90 readings with and without the project. By using the
L90 the Planning Board will most accurately consider the change
in the general environments, uninfluenced by random, infrequent and
unusually loud noises. Set forth below is a table which compares the
L90 readings, daytime and nighttime at receptor sites R4, R5
and R6.
The data is taken from Tables 2.6-2 and 2.6-4
of the SDEIS.
Compared to the SDEIS where Widewaters
attempted to understate the noise impacts by stating that the only change
at the receptors measured in Ldn was only 2.7 to 6.7 dB, a more accurate
reading using the L90 measurement show that increase will range
from a minimum of 7.3 to as high as 14.7. More importantly, of the six
important receptor measurements (day and night at each of the three
receptors) four will show increases greater than 10 dB. That increase, at
residential areas constitutes a perceived doubling of the existing sound
levels and is, by definition intrusive. As provided in the DEC Noise
Guidance, noise level increases greater than 10 dB should be
avoided.
4. The existing surrounding environment is
characterized by either existing residential properties or currently
vacant land zoned for residential purposes. Operation of Widewaters
Commons will significantly adversely impact current residential land uses
by more than doubling the existing sound levels. For properties that are
not currently developed the presence of Widewaters will adversely impact
their ability to be used for residential purposes since the increased
noise levels will be significantly higher than currently and inconsistent
with the quiet semi-rural environment that residents seek. If those
properties cannot be put to residential uses because the neighboring land
use is incompatible, there will be strong pressure to change the zoning on
those parcels and continue the spread of commercial uses that are not as
sensitive to higher noise levels. Thus, the initial introduction of a
large shopping center with dramatically increased noise levels will be the
proverbial camel’ nose under the tent - changing the character of the area
and making future residential development as envisioned in the
comprehensive plan and the zoning code, far less and attractive and
promoting the type of commercial sprawl that the comprehensive plan is
intended to prevent.
5. Considering the dramatic increase in noise
that the project will produce the Planning Board should deny approval for
creating an unmitigated adverse impact. At a minimum, the applicant must
be required to produce far greater noise mitigation of both the equipment
and the size of the project, including re-positioning the buildings
farther from property lines. In addition, contrary to the statement in the
SDEIS, further mitigation is required and the project must include
sound-buffering berms and other structures to mitigate the significant
adverse impacts the project will cause.
IV. Zoning and Design Standards
1. As noted previously, it is our
understanding that the Planning Board has received and is considering an
alternate design for the project, however those plans have not been made
available to KNGG and public comment has not been solicited. Therefore,
KNGG is at a disadvantage in its ability to comment upon those aspects of
the project. KNGG respectfully demands that it be provided copies of any
new design details and be given an opportunity to comment upon that
proposal. Until such time, KNGG’s comments on the zoning and design
elements of the project must be considered preliminary.
2. Reference is specifically made to the
comments of Howard Brandston, whose comments are attached hereto as Ex. B.
Mr. Brandston notes that the proposed lighting fixtures are out of scale
with the project and the surrounding community and will produce both light
pollution and a change in the character of the area. Widewaters must be
required to present a detailed assessment of the lighting impacts of the
project.
3. While Widewaters is apparently requesting
a variance from some of the design requirements of the zoning code, it has
failed to provide details of the alternatives to be considered. Widewaters
has only provided a design analysis and visual impact analysis of what it
is proposing, not what is otherwise required or less drastic variations
from the design standards. Without a comparative analysis of the
alternatives, it is impossible for the Planning Board to fulfill its SEQRA
obligations to take a hard look at the relative impacts of the proposals.
Widewaters must be directed to supplement its EIS with details of the
project in compliance with the newly adopted design
standards.
4. Needless to say Widewaters statements that
the new design standards were somehow foisted upon them must be
disregarded. As the record makes abundantly clear, Widewaters was the
moving force for the rezoning of this parcel in 2001 and specifically
requested that the project be considered under the current zoning code so
that it could benefit from the re-zoning and the accompanying increase in
the bulk restrictions to allow a project of this size. Having chosen the
path it sought to pursue, Widewaters must recognize that any hardship
associated with that decision is self-created and it must comply with the
new restrictions.
5. This is the first major project considered
in the town under the new zoning design standards. If those standards are
to have any meaning, they must be applied to projects of this magnitude
that have maximum impact upon the character and fabric of the town. A
developer of Widewaters’ stature has the means to comply with the town’s
vision of future development and must respect that vision. If the Planning
Board fails to require a developer with these resources to meet the
requirements of the new law, it will lose all credibility in attempting to
require small businesses to do the same, and the result would be a
complete destruction of the intent of the new zoning law.
6. Consistent with the foregoing is a
recognition that pursuant to the comprehensive plan, the fact that the
property is zoned for business uses and is of a given size is not the same
as a finding that it is appropriate for this scale of development. Many
other factors as outlined in the DEIS and SDEIS must be considered and
evaluated to determine if this specific development is appropriate. It is
critical to point out that when this parcel was re-zoned from agricultural
to business use, the Town Board did not undertake any review under SEQRA
for the re-zoning so there is no presumption that the full environmental
impacts of a full build-out of the parcel was ever considered. Therefore
the Planning Board has the full responsibility to determine if this
project is consistent not only with the zoning code, but also with the
comprehensive plan.
V. Conclusion
The Planning Board must carefully consider
not only these comments, but the other comments it has received in writing
and orally and must also consider the still unanswered questions from the
DEIS. When viewed as a whole and considering the enormous gaps in analysis
of the adverse environmental impacts of the project, it is clear that the
project as proposed does not minimize, avoid or mitigate that adverse
environmental impacts to the maximum extent practicable and as such the
Planning Board must decline to approve the project.
Daniel Mackay, Director of Public Policy Preservation League of New York State 44 Central Avenue, Albany, NY 12206 (518) 462-5658 Edwin R. Simonsen, Chair Town of Kinderhook Planning Board Town Hall, Box P, Niverville, New York 12130 September 14, 2003 RE: Public Comment Opportunity regarding the Proposed Widewaters Commons Shopping Center, Town of Kinderhook Chairman Simonsen, and members of the Town of Kinderhook Planning Board: I am writing to comment on the SDEIS for the proposed Widewaters Commons Shopping Center in the Town of Kinderhook. The Preservation League of New York State is the statewide non-profit organization dedicated to the protection of New York’s diverse and rich heritage of historic buildings, districts and landscapes. Increasingly in this age of sprawl and deteriorating architectural standards, we are asked to comment on planning and zoning issues that appear to negatively impact the distinct community character of both urban and rural communities. I have monitored the Widewaters Commons proposal over the past year at the request of several local residents, and toured the proposed site earlier this summer. At this time, I would like to note several concerns the Preservation League holds about the proposal, while also reserving the right to make further comment by the September 15th 2003 public comment deadline. Most significantly, I must characterize the "five-legged" roundabout proposed by NYS Department of Transportation (DOT) for this intersection as experimental in nature and thus an unproven tool for safely delivering traffic to, from, and by the proposed Widewaters Commons. Roundabouts are a new tool in DOT’s engineering toolbox and have met with some public concern as to their safety and effectiveness as an engineering solution to intersections. To exacerbate the effective use of this new "solution" with a fifth leg of an intersection would seem to merit greater consideration and proof than is given this solution as proposed under Alternative 1 and 2 in the SDEIS. The challenges of engineering a solution to the traffic challenges of this upgraded intersection underscore the risk of irrevocably losing the opportunity to make the Rt. 9/Rt. 9H intersection an attractive and model gateway to the community and historic core of Kinderhook. Already, the road corridor along Rt. 9 has been degraded by low-grade commercial sprawl, lackluster corporate architectural design, all-too-prominent parking facilities, and ineffective landscaping. The question before the Planning Commission is whether to alleviate this condition, or exacerbate it. With effective design, this gateway intersection could be reclaimed, and prove an attractive welcome to an impressive corner of Columbia County. The Widewaters Commons proposal, however, will add a dominating site plan to this intersection, marring mountain views to the west and inserting acres of parking and bland architecture in their place. Prominence, visibility and traffic volume are all likely reasons for The Widewaters Group to prioritize development of their services on this site, but would residents of Kinderhook not prefer an alternate location where the proposed development would directly abut existing uses that are more compatible to the size, scale, and visual impact of Widewaters Commons, rather than mar the Town’s first clear view of the Catskills? Finally, I must note that the architectural renderings of the Commons reflect only minimal concessions and creativity regarding the Town of Kinderhook’s Zoning and Design Standards. The designs proposed here meet neither the spirit nor letter of the law, and it is a continuing shame that corporate architecture – particularly that of regionally-based corporations that purport true pride and continuing investment in their home communities – fail to honor the communities they site in with architectural designs that contribute to community character rather than detract from it. It is my hope that these comments and those of others concerned for the impacts of the Widewaters Commons proposal are given the full consideration of the Planning Board, such that the most appropriate site and design are mandated for this proposal. Sincerely, Daniel Mackay, Director of Public Policy Preservation League of New York State
| |||||||||||||||||||||||||||||||||||||||||||||||||