a not-for-profit corporation   
PO Box 424    Kinderhook NY  12106    518-758-2646    KNGG@berk.com

 
WIDEWATERS COMMONS WIDEWATERS DEIS WIDEWATERS SDEIS ROUNDABOUT KNGG FINDINGS ARTICLE 78 ABOUT KNGG MEMBERSHIP KNGG CONCERT BENEFIT KNGG Home Page
PAST ISSUES Home Page
COMMENTS ON WIDEWATERS SDEIS
 
 
COMMENTS
ON THE
WIDEWATERS COMMONS
SDEIS
 
September 15, 2003 
Prepared by: Young, Sommer ..., LLC
Attorneys for KNGG
Executive Woods
5 Palisades Drive
Albany, NY 12205
518) 438-9907
Jeffrey S. Baker, Esq.
 
 I. Introduction Kinderhook Neighbors for Good Growth ("KNGG") submit these comments on the Supplemental Draft Environmental Impact Statement ("SDEIS") for the Widewaters Commons Shopping Center ("Widewaters" or the "Project"). These comments are in addition to the comments submitted in November 2002 on the original DEIS. At that time, KNGG noted the glaring deficiencies in many aspects of the DEIS and the project itself and protested that the Planning Board could not continue its SEQRA review without correcting the deficiencies of the DEIS in a Supplemental EIS. Fortunately the Planning Board recognized its error in accepting the DEIS and ordered the preparation of a SEIS. However, the scope of the SDEIS was limited and did not address all of the deficiencies in the DEIS. Moreover, Widewaters was not directed to respond to the DEIS comments as part of the SDEIS. Therefore, KNGG reasserts its comments of November 2002 and puts Widewaters and the Planning Board on notice that any new information contained in a FEIS which was not previously available for public comment, must be provided in another SEIS to allow for meaningful comment.
 
While the foregoing comment concerned missing elements from the DEIS which were not covered in the SDEIS, there are also on-going problems with new material submitted since the SDEIS was accepted and released for public comment. Specifically, upon information and belief it appears that Widewaters has submitted architectural renderings and design details for the project which are completely different from what is included in the SDEIS. Those submittals have not been distributed to involved agencies or interested parties and thus those parties have not been given an opportunity to comment on the submissions. Until those materials are made publicly available and a reasonable time frame is provided for comment, the Planning Board cannot consider continued revisions to the design elements of the project.
A
Taken as a whole and evidenced by the numerous public comments submitted to date, the Widewaters project is out of scale with the community and is located on a parcel which exacerbates its problems of scale without providing sufficient community benefits. Contrary to the tone of much of the public discussion fomented by Widewaters, this is not an issue of the desirability of a new supermarket in Kinderhook. KNGG has long supported diversity and competition in shopping alternatives. The issue is the size of the project and the unnecessary problems it will cause the community by being located on this parcel. As the SDEIS demonstrates, the location at a problematic intersection only compounds the existing problems and the preferred way of dealing with the situation by a roundabout will fundamentally alter the character of this section of Kinderhook and change the traffic patterns in the area. There are significant concerns as to whether such a change is beneficial and desired by the majority of the people in the town. Notwithstanding general statements of support from NYSDOT, this is not a NYSDOT project but rather a proposal from an private developer and NYSDOT has simply opined that the only possible means of dealing with the traffic is by a roundabout. It is entirely within the Planning Board’s authority to determine that this project, with its environmental problems is inappropriate for this site and not permitted. It is not the responsibility of the Planning Board to make a project work on a difficult site - it is the responsibility of the applicant to choose a site that minimizes or avoids adverse impacts. Where the developer has chosen an inappropriate site, it is incumbent upon the Planning Board to reject the project.
 
Set forth below are KNGG’s comments on the SDEIS organized by the subject matter. Also attached hereto are additional comments from Sara Richards and Mark Litteken. Ms. Richards and Mr. Litteken are on the Board of Directors of KNGG and the attached comments were also presented at the August 27, 2003 public hearing on the SDEIS. Also attached are comments on the traffic section provided by KNGG’s traffic consultant Vollmer Associates. Finally, the comments of Howard Brandston regarding the impacts from and design of the project lighting are also included. Mr. Brandston’s comments were also presented at the public hearing. In addition to these comments, many members of KNGG are sending comments directly to the Planning Board and should be given full consideration.
 
II. Traffic
KNGG’s comments on traffic are supported by the analysis provided by Vollmer Associates, LLP.
A copy of Vollmer’s comments are attached as Ex. A.
 
1. As noted in KNGG’s comments on the DEIS, Widewaters failed to compile accurate data for existing traffic conditions by failing to collect data during a period of normally heavy traffic. Instead, Widewaters collected data in mid-August when school traffic is non-existent and other traffic is traditionally lighter due to vacation schedules. In the SDEIS Widewaters claims to have supplemented its traffic analysis with additional traffic counts, however that data is not supplied in the SDEIS.
 
2. In the DEIS, the project only proposed adding project access to the existing intersection and changing the signalization. As such it was acceptable for that traffic study to only consider the impact from the project on the intersection and thus only look at the afternoon peak travel time to assess the project’s impact. In the SDEIS, however, the proposal is for a roundabout that will need to operate under all conditions and not just those associated with peak operation of the shopping center. As lead agency, the Planning Board has the responsibility to determine that this proposed change to the primary intersection in the town works under all conditions, particularly the morning commute. However, the SDEIS is absolutely devoid of any information on morning traffic conditions and the impacts from the roundabout on the morning commute. Widewaters has not supplemented its traffic study with a morning traffic count and has not modeled the roundabout for the morning peak. As noted by Vollmer, such an analysis is a critical flaw as one cannot extrapolate morning conditions from evening conditions and without raw data and a model run, it is impossible to predict what the effect will be. Furthermore, the data supplied by NYSDOT is not a complete traffic study and cannot substitute for a comprehensive analysis. If this project were to enjoy further consideration, Widewaters must be directed to conduct a complete traffic study that includes AM peak travel.
 
3. Vollmer also points out that Widewaters’ traffic analysis is essentially comparing apples to oranges as it attempts to argue that use of the roundabout will provide an acceptable LOS. Vollmer notes that Widewaters has not supplied the necessary reports from its computer model using the Webster Method which is the only accepted means of evaluating compliance with the Highway Capacity Manual LOS. The HCM does not use the percentile delay method for LOS. There can be no independent verification of Widewaters’ representations without the proper computer runs presented in the accepted format. Considering Widewaters’ less than stellar record of refusing to provide details and supporting information to the Planning Board and its misrepresentation of the facts of its project, it is necessary that the Planning Board’s consultants and the public have all of the necessary information to verify Widewaters’ claims.
 
4. Vollmer also notes that Widewaters has not used NYSDOT’s standard software package for analyzing roundabouts - Rodel. Widewaters should re-analyze the roundabout using the standard software package and provide the output data for review.
5. In less than 20 years, by Widewaters own analysis, the roundabout will be operating beyond capacity and in a failure condition. Widewaters has refused to provide even preliminary design details to show that there is an adequate right-of-way for the current design, let alone future needs. The Planning Board should require a complete survey demonstrating sufficient right-of-way for now and the future. Any possible relocation of the roundabout into the Widewaters project must be taken into account now and changes made to the Widewaters site plan since such changes will alter the design of the interior road-way, parking and the aesthetics of the project.
 
6. Vollmer notes that roundabouts remain a novel approach without a lot of practical experience in their long-term viability, especially when they involve five-legged intersections and NYSDOT also considers them as "experimental". If the project were to be approved, then the Planning Board should require Widewaters to undertake a post-construction traffic study to gauge the effectiveness of the roundabout and provide for any alterations to the roundabout to correct any design deficiencies. The study should be conducted 2 years after the project is completed and include new traffic counts, capacity analysis and a comparison of the actual results to those of the original study and should include an accident analysis. Widewaters should be required to post a bond at this time to cover both the cost of the post-construction study and the potential necessary improvements. There is precedent for such a requirement on the developer. When Pyramid was proposing the Palisades Center Mall in Nyack, the Planning Board required Pyramid to post a bond for a post-construction traffic study and the cost of further signalization if it was determined that it was required.
 
7. The SDEIS does not attribute any growth factors for the driveways into the project when it is calculating future growth in the area and capacity of the roundabout to handle the growth. Unlike an office park or similar type of development, use of this shopping center, especially the supermarket will continue to grow as the area grows and it is simplistic to claim that the trip generation figures and use of the driveways will not change in the future. As Vollmer notes, a sensitivity analysis of the driveways is required.
8. It does not appear that the roundabout has been designed in accordance with NYSDOT and FHWA guidelines for roundabouts. While strict compliance with those guidelines is not required, Widewaters must clearly discuss where it is diverging from those guidelines, explain the need for the difference and the potential impacts from the break with the guidelines.
 
9. The SDEIS is less than clear about Widewaters’ responsibility for constructing the improvements if they are approved. Widewaters must specifically commit to paying for all of the necessary traffic improvements including the roundabout and the new traffic signal at the intersection of Route 9 and Main Street. Particularly in regard to the latter, while that intersection is already operating at an undesirable LOS, by Widewaters’ own analysis, its project will exacerbate the situation and Widewaters is responsible for the additional costs. While KNGG does not support approval of the project, any approval must include a condition that a building permit for the project will not be issued until Widewaters has obtained all necessary permits for the traffic improvements and a Certificate of Occupancy should not be issued until all of the traffic improvements have been completed. These conditions are necessary to assure that if the project is built, all of the mitigation measures are properly in place before the impacts of the project are imposed upon the town.
 
III. Noise
In its noise impact analyses, Widewaters again appears to comply with the mandate of the Planning Board and on initial impression gives the indication of presenting a comprehensive and accurate assessment of the noise impacts from the project. However, a careful consideration of Widewaters’ own analyses as well as an accurate application of DEC’s noise assessment guidelines makes it apparent that the project will result in significant noise impacts on surrounding properties. After project completion the noise generated from Widewaters Commons will be intrusive and objectionable to neighboring residential uses and will effectively preclude development of currently vacant property in accordance with its current zoning.
 
1. The SDEIS understates the noise impacts by mischaracterizing the thresholds identified in DEC’s Guidance Document "Assessing and Mitigating Noise Impacts" Revised June 3, 2003. Widewaters focuses on using the Leq sound measurement which is an equalized sound pressure reading over time and attempts to average out the sound levels. By contrast the L90 measurement is generally accepted as the best measure of background sound since it establishes the level of sound exceeded 90 % of the time. DEC’s guidance document recognizes the use of the L90 as a better measurement tool. (DEC Guidance, p. 12).
 
2. The SDEIS also provides an incomplete catalogue of the intrusiveness of noise levels. While the SDEIS properly quotes the DEC guidance on increases of 3-6 dB, it omits to point out that increases greater than 6 dB require careful scrutiny and assessment and "that increases approaching 10 dB result in a perceived doubling of Sound Pressure Level. . . . An increase of 10 dB(A) deserves consideration of avoidance and mitigation measures in most cases" (DEC Noise Guidance p. 13-14). Furthermore, the DEC Guidance notes that increases of 5-10 dB are considered intrusive and increases over 10 dB are very noticeable.
 
3. Using Widewaters own analysis but looking at the measurements which provide the most accurate picture of the change in the environment, it is clear that the project will have a significant and unmitigated adverse impact. To measure the change in the background noise level a comparison must be made to the daytime and nighttime L90 readings with and without the project. By using the L90 the Planning Board will most accurately consider the change in the general environments, uninfluenced by random, infrequent and unusually loud noises. Set forth below is a table which compares the L90 readings, daytime and nighttime at receptor sites R4, R5 and R6.
 
The data is taken from Tables 2.6-2 and 2.6-4 of the SDEIS.
 

Site R4

Site R5

Site R6

 

Existing

Proposed

Change

Existing

Proposed

Change

Existing

Proposed

Change

Daytime

L90

45

59.7

14.7

42.8

53

10.2

47.2

54.5

7.3

Night

L90

40.5

52

11.5

40.2

48.2

8

41.0

51.6

10.6

 
Compared to the SDEIS where Widewaters attempted to understate the noise impacts by stating that the only change at the receptors measured in Ldn was only 2.7 to 6.7 dB, a more accurate reading using the L90 measurement show that increase will range from a minimum of 7.3 to as high as 14.7. More importantly, of the six important receptor measurements (day and night at each of the three receptors) four will show increases greater than 10 dB. That increase, at residential areas constitutes a perceived doubling of the existing sound levels and is, by definition intrusive. As provided in the DEC Noise Guidance, noise level increases greater than 10 dB should be avoided.
 
4. The existing surrounding environment is characterized by either existing residential properties or currently vacant land zoned for residential purposes. Operation of Widewaters Commons will significantly adversely impact current residential land uses by more than doubling the existing sound levels. For properties that are not currently developed the presence of Widewaters will adversely impact their ability to be used for residential purposes since the increased noise levels will be significantly higher than currently and inconsistent with the quiet semi-rural environment that residents seek. If those properties cannot be put to residential uses because the neighboring land use is incompatible, there will be strong pressure to change the zoning on those parcels and continue the spread of commercial uses that are not as sensitive to higher noise levels. Thus, the initial introduction of a large shopping center with dramatically increased noise levels will be the proverbial camel’ nose under the tent - changing the character of the area and making future residential development as envisioned in the comprehensive plan and the zoning code, far less and attractive and promoting the type of commercial sprawl that the comprehensive plan is intended to prevent.
 
5. Considering the dramatic increase in noise that the project will produce the Planning Board should deny approval for creating an unmitigated adverse impact. At a minimum, the applicant must be required to produce far greater noise mitigation of both the equipment and the size of the project, including re-positioning the buildings farther from property lines. In addition, contrary to the statement in the SDEIS, further mitigation is required and the project must include sound-buffering berms and other structures to mitigate the significant adverse impacts the project will cause.
 
IV. Zoning and Design Standards
 
1. As noted previously, it is our understanding that the Planning Board has received and is considering an alternate design for the project, however those plans have not been made available to KNGG and public comment has not been solicited. Therefore, KNGG is at a disadvantage in its ability to comment upon those aspects of the project. KNGG respectfully demands that it be provided copies of any new design details and be given an opportunity to comment upon that proposal. Until such time, KNGG’s comments on the zoning and design elements of the project must be considered preliminary.
 
2. Reference is specifically made to the comments of Howard Brandston, whose comments are attached hereto as Ex. B. Mr. Brandston notes that the proposed lighting fixtures are out of scale with the project and the surrounding community and will produce both light pollution and a change in the character of the area. Widewaters must be required to present a detailed assessment of the lighting impacts of the project.
 
3. While Widewaters is apparently requesting a variance from some of the design requirements of the zoning code, it has failed to provide details of the alternatives to be considered. Widewaters has only provided a design analysis and visual impact analysis of what it is proposing, not what is otherwise required or less drastic variations from the design standards. Without a comparative analysis of the alternatives, it is impossible for the Planning Board to fulfill its SEQRA obligations to take a hard look at the relative impacts of the proposals. Widewaters must be directed to supplement its EIS with details of the project in compliance with the newly adopted design standards.
 
4. Needless to say Widewaters statements that the new design standards were somehow foisted upon them must be disregarded. As the record makes abundantly clear, Widewaters was the moving force for the rezoning of this parcel in 2001 and specifically requested that the project be considered under the current zoning code so that it could benefit from the re-zoning and the accompanying increase in the bulk restrictions to allow a project of this size. Having chosen the path it sought to pursue, Widewaters must recognize that any hardship associated with that decision is self-created and it must comply with the new restrictions.
 
5. This is the first major project considered in the town under the new zoning design standards. If those standards are to have any meaning, they must be applied to projects of this magnitude that have maximum impact upon the character and fabric of the town. A developer of Widewaters’ stature has the means to comply with the town’s vision of future development and must respect that vision. If the Planning Board fails to require a developer with these resources to meet the requirements of the new law, it will lose all credibility in attempting to require small businesses to do the same, and the result would be a complete destruction of the intent of the new zoning law.
 
6. Consistent with the foregoing is a recognition that pursuant to the comprehensive plan, the fact that the property is zoned for business uses and is of a given size is not the same as a finding that it is appropriate for this scale of development. Many other factors as outlined in the DEIS and SDEIS must be considered and evaluated to determine if this specific development is appropriate. It is critical to point out that when this parcel was re-zoned from agricultural to business use, the Town Board did not undertake any review under SEQRA for the re-zoning so there is no presumption that the full environmental impacts of a full build-out of the parcel was ever considered. Therefore the Planning Board has the full responsibility to determine if this project is consistent not only with the zoning code, but also with the comprehensive plan.
 
V. Conclusion
The Planning Board must carefully consider not only these comments, but the other comments it has received in writing and orally and must also consider the still unanswered questions from the DEIS. When viewed as a whole and considering the enormous gaps in analysis of the adverse environmental impacts of the project, it is clear that the project as proposed does not minimize, avoid or mitigate that adverse environmental impacts to the maximum extent practicable and as such the Planning Board must decline to approve the project.


Daniel Mackay, Director of Public Policy

Preservation League of New York State

44 Central Avenue, Albany, NY 12206

(518) 462-5658

Edwin R. Simonsen, Chair

Town of Kinderhook Planning Board

Town Hall, Box P, Niverville, New York 12130

September 14, 2003

RE: Public Comment Opportunity regarding the Proposed Widewaters Commons Shopping Center, Town of Kinderhook

Chairman Simonsen, and members of the Town of Kinderhook Planning Board:

I am writing to comment on the SDEIS for the proposed Widewaters Commons Shopping Center in the Town of Kinderhook. The Preservation League of New York State is the statewide non-profit organization dedicated to the protection of New York’s diverse and rich heritage of historic buildings, districts and landscapes. Increasingly in this age of sprawl and deteriorating architectural standards, we are asked to comment on planning and zoning issues that appear to negatively impact the distinct community character of both urban and rural communities.

I have monitored the Widewaters Commons proposal over the past year at the request of several local residents, and toured the proposed site earlier this summer. At this time, I would like to note several concerns the Preservation League holds about the proposal, while also reserving the right to make further comment by the September 15th 2003 public comment deadline.

Most significantly, I must characterize the "five-legged" roundabout proposed by NYS Department of Transportation (DOT) for this intersection as experimental in nature and thus an unproven tool for safely delivering traffic to, from, and by the proposed Widewaters Commons. Roundabouts are a new tool in DOT’s engineering toolbox and have met with some public concern as to their safety and effectiveness as an engineering solution to intersections. To exacerbate the effective use of this new "solution" with a fifth leg of an intersection would seem to merit greater consideration and proof than is given this solution as proposed under Alternative 1 and 2 in the SDEIS.

The challenges of engineering a solution to the traffic challenges of this upgraded intersection underscore the risk of irrevocably losing the opportunity to make the Rt. 9/Rt. 9H intersection an attractive and model gateway to the community and historic core of Kinderhook. Already, the road corridor along Rt. 9 has been degraded by low-grade commercial sprawl, lackluster corporate architectural design, all-too-prominent parking facilities, and ineffective landscaping. The question before the Planning Commission is whether to alleviate this condition, or exacerbate it. With effective design, this gateway intersection could be reclaimed, and prove an attractive welcome to an impressive corner of Columbia County.

The Widewaters Commons proposal, however, will add a dominating site plan to this intersection, marring mountain views to the west and inserting acres of parking and bland architecture in their place. Prominence, visibility and traffic volume are all likely reasons for The Widewaters Group to prioritize development of their services on this site, but would residents of Kinderhook not prefer an alternate location where the proposed development would directly abut existing uses that are more compatible to the size, scale, and visual impact of Widewaters Commons, rather than mar the Town’s first clear view of the Catskills?

Finally, I must note that the architectural renderings of the Commons reflect only minimal concessions and creativity regarding the Town of Kinderhook’s Zoning and Design Standards. The designs proposed here meet neither the spirit nor letter of the law, and it is a continuing shame that corporate architecture – particularly that of regionally-based corporations that purport true pride and continuing investment in their home communities – fail to honor the communities they site in with architectural designs that contribute to community character rather than detract from it.

It is my hope that these comments and those of others concerned for the impacts of the Widewaters Commons proposal are given the full consideration of the Planning Board, such that the most appropriate site and design are mandated for this proposal.

Sincerely, 

Daniel Mackay, Director of Public Policy

Preservation League of New York State



*  *  *