KNGG FINDINGS
KNGG FINDINGS
on the Widewaters Commons application
Part I of the suggestions deals with findings. Any one finding or all can be used as a valid reason to deny the project and would stand up in court.
Part II deals with conditions. It is added in the event that the Planning Board might approve the project. If so, KNGG says that the these conditions should be met. The conditions should be required before any vote is taken. If the developer refuses to meet the "conditions," the project should be denied.
The KNGG
findings suggestions statement was presented to the Planning
Board for its consideration at its meeting of July 15, 2004 by attorney Jeff
Baker.
Young,
Sommer ... LLC
|
JEFFREY S. BAKER DAVID C. BRENNAN MICHAEL J.
MOORE KENNETH S.
RITZENBERG DEAN S. SOMMER DOUGLAS H. WARD KEVIN M. YOUNG JOSEPH F.
CASTIGLIONE JAMES A. MUSCATO,
II ROBERT A.
PANASCI |
Young, Sommer, Ward, Ritzenberg, Baker & Moore,
LLC COUNSELORS AT LAW ALL
WRITTEN CORRESPONDENCE TO: Executive
Woods, Five Palisades Drive, Albany,
NY
12205 Phone:
518-438-9907 • Fax: 518-438-9914 Saratoga Office: 468 Broadway, Saratoga Springs, NY
12866 Phone:
518-580-0163 |
Of
Counsel Sonya K. del Peral Elizabeth M. Morss Thomas J. Neidl Kristin Carter
Rowe Lawrence R.
Schillinger David R. Wooley
Nicole A. Banagan,
Paralegal Laura K. Ross,
Paralegal Vicki G. Schlierer, Paralegal |
jbaker@youngsommer.com
July 15, 2004
Mr. Edward Simonsen,
Chairman
Town of Kinderhook Planning Board
P.O. Box
P
Town Hall
Niverville, New York
12130
Re: Widewaters - Findings Suggestions
Dear Mr. Simonsen and
Members of the Planning Board:
On behalf of Kinderhook Neighbors for Good Growth (KNGG) we are
submitting the following points for the Planning Board to consider as it is
developing its SEQRA Findings for the project. It is KNGG’s fundamental position that
despite changes in the project over the last two years, the adverse
environmental impacts of the project have not been avoided, minimized or
mitigated to the maximum extent practicable consistent social, economic and
other essential considerations.
That is the standard that the Planning Board must apply and it is evident
that the Planning Board has the authority to determine that on balance the
adverse impacts of the project outweigh any purported benefits to the
community. In short, the project is
too large and in the wrong location in the town. It is the location which produces the
insurmountable problems for town - at a different location, the project may work
- but at this location it presents serious problems and those problems will only
be exacerbated if the project is built.
Set forth below are our proposed statements to be included in the
findings statement which will support denial of the project. Also set forth below are proposed
findings consisting of conditions which should, at a minimum, be imposed if the
Planning Board decides to approve the project. KNGG’s offer of these proposed
conditions does not mean that KNGG supports the project or that adoption of
these conditions will allow the Planning Board to satisfy its legal requirements
under SEQRA, and KNGG specifically reserves its right to seek judicial relief
should it so decide. Nevertheless,
these conditions will help to mitigate the significant adverse impacts of the
project. We also note that we only
received a copy of the accepted FEIS yesterday and we are still reviewing that
document. Therefore we reserve our
right to supplement these suggestions in the coming
days.
I. Reasons for
Denial
A. Traffic
1.
The FEIS has demonstrated that the project as proposed will result in
significant adverse environmental impacts to the traffic conditions in the Town
of Kinderhook. The applicant
originally proposed a 5-legged intersection for the intersection of Routes 9, 9H
and State Farm Road along with the entrance to the shopping center. That proposal was found to be fatally
flawed by DOT, the Town’s consultants and consultants retained by interested
parties. The applicant has altered
its proposal to provide for a 5-legged roundabout to replace the existing
signalized intersection. That
proposal will dramatically change the nature of the road network in the
community and the Planning Board is not certain that such a proposal is in the
best interest of the town.
2.
The applicant has not provided a detailed traffic study of the morning
traffic that will be passing through the roundabout and the ability of the
roundabout to handle that level of traffic growth into the future. While the applicant has proposed a
two-lane roundabout for the western edge of the roundabout to handle southbound
traffic, there is no corresponding provision for increased growth for the
northbound traffic.
3.
The applicant’s traffic studies that were conducted used a 2% annual
growth factor although DOT data at the time indicated that the annual growth
factor was 2.4%. Furthermore, a
more recent traffic study prepared for a proposed Dunkin Donuts at the same
intersection, demonstrated that the most annual growth factor is 5%. The Planning Board finds that for the
design of such a critical element of the town’s highway infrastructure the most
conservative growth factor should be used which reflects the recent surge in
growth in the Town and Columbia County and the importance of the 9/9H corridor
to regional transportation.
4.
Construction of the roundabout and its expected operation as described by
the applicant’s experts and DOT is to provide a relatively seamless stream of
traffic through the roundabout and onto the roads it services. While that may relieve congestion at
that intersection it will have the negative impact of increasing congestion on
side roads where cars will not be able to enter traffic because of the constant
flow. Currently the flow is
interrupted by the traffic lights, providing breaks for cars turning north on
Rt. 9 from Maple Road and other roads.
5.
The provision for a partial two-lane roundabout has the serious potential
of providing a safety problem with merging traffic, particularly vehicles
leaving the shopping center and traveling to Route 9 north, State Farm Road and
Route 9 South. All of that traffic
will be required to cross over a lane to get to the single lane completing the
roundabout. That traffic will be
competing with traffic already in the roundabout, especially traffic crossing
lanes to proceed to Route 9H south.
6.
The Planning Board concerns are not alleviated by DOT’s statements in
support of the roundabout. This is
not a DOT sponsored project and the DOT project manager admitted to the Planning
Board that he did not undertake a comprehensive traffic study and did not
consider the impacts of the roundabout on adjoining roads or the entrances to
nearby businesses.
7.
The EIS has failed to adequately consider all of the cumulative impacts
of other projects currently proposed and likely to be proposed for the same
area, particularly the pending Dunkin Donuts application that will exacerbate
traffic problems in the immediate area.
8.
The EIS recognizes that the intersection of Route 9 and Main Street while
already at a Level of Service “F” will be significantly worsened by the traffic
generated by the project. While the
applicant originally offered to pay a fair share for the installation of a
traffic signal at that intersection, it has recently declined to do so or assure
that a signal will be installed before the project is completed. While the applicant is not responsible
for the current condition at the intersection, it is responsible for making the
condition at that intersection significantly worse. Without assuring signalization, this is
an unmitigated adverse impact that cannot be condoned by the Planning
Board.
B. Visual Impacts/Open
Space
1.
The project site presents unique views of the Catskill Mountains which
are important to the character of the Town and are highly valued by the Town’s
residents. Construction of a
project of this size serves to permanently alter the viewshed and change the
character of the town. The Planning
Board recognizes that the Town Board re-zoned the parcel in 2001, but also notes
that the Town did not undertake any environmental review at the time and thus
left it to the Planning Board to make a determination as to the impacts of
development on the parcel at the time of a particular application. A smaller less intensive use of the site
would maintain the visual character.
2.
The landscaping and lighting plan do not provide adequate mitigation for
the visual impacts of the project. The proposed vegetation is too sparse and
immature to provide meaningful screening.
The proposed lighting standards are too tall and will provide unnecessary
glare and light pollution changing the character of the
area.
II. Proposed
Conditions
A. Traffic
1.
The safety and effectiveness of the roundabout are unproven and
experience at other locations demonstrates that planning often does not reflect
reality. Therefore it will be
necessary for a post-development study of the roundabout and a provision for
improvements or alterations of the roundabout. Since the project is being constructed
by Widewaters and not with public funds, there is no assurance that public funds
will be available for such work.
Therefore, Widewaters must post a bond or other security in the amount of
_______ for a study of the roundabout’s safety and effectiveness to be conducted
one-year after the roundabout and shopping center are in operation. The bond shall be in a sufficient amount
to cover the cost of the study and any necessary improvements to the roundabout
including additional lanes, striping, reconfiguration and
signage.
2.
Education of residents as to how to navigate a roundabout is critical for
its success and to minimize accidents.
Widewaters shall provide a public information campaign to the residents
of the Town that shall, at a minimum, include a safety brochure mailed to each
residence in the Town.
3.
The traffic light at Main Street and Route 9 is critical to mitigating
the adverse impacts of the project and it is not the Town’s responsibility to
obtain funding for that light, nor is it the Town’s responsibility to obtain
other public funding. Since this is
a problem that will be significantly worsened by Widewaters, it shall be a
condition of the issuance of Certificate of Occupancy for the first building in
the shopping center that a traffic light be installed at that intersection. Widewaters can either pay for the entire
light or seek funding from DOT, however, installation of the light is necessary
before the project begins operation and generating significant levels of
traffic.
B. Open Space and
Habitat
1.
In the DEIS the applicant represented that the rear 9 acres of the site
would be maintained as open space and as mitigation for the loss of wildlife
habitat, except for the location of septic systems and wells. To assure that the adverse impacts to
loss of open space and wildlife habitat are mitigated as represented in the EIS,
the applicant will be required to place a deed restriction on that portion of
the property precluding its future development in any manner greater than that
shown of the site plan approved for the
project.
C. Visual
Impacts
1.
To mitigate the visual impacts of the lighting of the project the maximum
height of the light poles in the parking lot shall be 12 feet measured from the
ground level to the height of the fixture.
We respectfully request that the Planning Board incorporate these
findings and deny the project or at the minimum include these conditions for
approval.
Very truly yours,
Jeffrey S. Baker